- Capacity
- 20 MW
- Target operation
- —
- Technology
- Electrolysis
- Country
- Germany
- Development stage
- Feasibility
Country scale
#86 by recorded MW among 219 projects with capacity recorded in this country.
All stages are included. Capacity does not describe current production.
Project details
- Product
- Hydrogen
- Production capacity
- 3.47 ktpa
Sources (7)
- IPCEI Hydrogen Observatory
IPCEI Hydrogen Observatory
Original value: construction planned by 2028; commissioning stated by 2028
- Hydrogenious - Green Hydrogen @ Blue Danube (DE59)
IPCEI Hydrogen Observatory
Original value: construction planned by 2028; commissioning stated by 2028
- IEA Hydrogen Production Projects 2026 (preserved CSV edition, received 2026-10-24)
International Energy Agency · As of 2026-06-18
Original value: Hydrogen (Product: Hydrogen)
Original value: 20 MW
Original value: Feasibility
Original value: 3.4650666666666665 kt H2/y (Product: Hydrogen)
Published value: 3.465 kt H2/y
- Hydrogenious LOHC Technologies GmbH
Hydrogenious LOHC Technologies GmbH
Original value: The FEED phase is planned to be completed in the second half of 2026 which will represent an important milestone to reach FID (Final Investment Decision) of the “Green Hydrogen @ Blue Danube” project. Following a positive FID, the construction phase will begin on site.
Original value: Main scope of the project is the construction of an LOHC hub in southern Bavaria by 2028
Original value: FEED phase planned for completion in the second half of 2026; construction follows a positive FID
- IPCEI: Hydrogenious LOHC receives multi-million grant for Green Hydrogen @ Blue Danube
Hydrogenious LOHC Technologies GmbH
Original value: The FEED phase is planned to be completed in the second half of 2026 which will represent an important milestone to reach FID (Final Investment Decision) of the “Green Hydrogen @ Blue Danube” project. Following a positive FID, the construction phase will begin on site.
Original value: FEED phase planned for completion in the second half of 2026; construction follows a positive FID
Original value: Main scope of the project is the construction of an LOHC hub in southern Bavaria by 2028
- IEA Hydrogen Production Projects 2026
International Energy Agency
Original value: Hydrogen (Product: Hydrogen)
Original value: Water electrolysis (Technology: Water electrolysis)
Original value: 20MW (Announced Size)
Original value: 20 MWel
Original value: 4444.444444444444 (Capacity (Nm³ H₂/h))
- International Energy Agency
International Energy Agency
Original value: Hydrogen (Product: Hydrogen)
Original value: Water electrolysis (Technology: Water electrolysis)
Original value: 4444.444444444444 (Capacity (Nm³ H₂/h))
Sources (2)
- Hydrogenious - Green Hydrogen @ Blue Danube (DE59)
IPCEI Hydrogen Observatory
Original value: Location
- International Energy Agency
International Energy Agency
Original value: Location
Projects in Germany
Major projects: operating and FID first, then by recorded capacity.
- Ostfriesland electrolysis / Clean Hydrogen Coastline - Electrolysis East FrisiaUnder construction280 MW
- GET H2 Nukleus (Phase 3)FID / Construction100 MW
- Hamburg Green Hydrogen Hub (HGHH) project - old Moorburg plantUnder construction100 MW
- REFHYNE (Phase 2)FID / Construction100 MW
- SALCOS - first expansion - phase 1FID / Construction100 MW