Ostfriesland electrolysis / Clean Hydrogen Coastline - Electrolysis East Frisia
280 MW · PEM · Germany
Under construction · counted as FID / Construction
- Capacity
- 280 MW
- Target operation
- —
- Technology
- PEM
- Country
- Germany
- Development stage
- Under construction · counted as FID / Construction
Sources: original names
Original name: Elektrolyse Ostfriesland / Clean Hydrogen Coastline – Electrolysis East Frisia
Country scale
#24 by recorded MW among 219 projects with capacity recorded in this country.
- AquaVentus (completion)9,972 MW
- Wasserstoffpark Lingen1,500 MW
- Ostfriesland electrolysis / Clean Hydrogen Coastline - Electrolysis East Frisia280 MW
All stages are included. Capacity does not describe current production.
Project details
- Function
- Production
- Production capacity
- 42 ktpa
- Scale
- Demonstration
Sources (9)
- Emden electrolyzer – hydrogen economy in East Frisia
Clean Hydrogen Coastline / EWE
Original value: Water electrolysis (Technology: Water electrolysis)
Original value: heavy-duty transport
Original value: Renewable (Electricity source: Renewable)
Original value: Lower Saxony (Niedersachsen)
Original value: Lower Saxony (Niedersachsen) (Site: Lower Saxony (Niedersachsen))
Original value: approximately 1,000,000,000 kWh per year (approximately 1 TWh)
Original value: Emden (Site: Emden)
- IEA Hydrogen Production Projects 2026 (preserved CSV edition, received 2026-10-24)
International Energy Agency · As of 2026-06-18
Original value: Other industries (Product: Hydrogen)
Original value: PEM
Original value: 2027
Original value: Emden, Lower Saxony, Germany (Site: Emden, Lower Saxony, Germany)
Original value: 280 MW
Original value: PEM electrolyser (Technology: PEM electrolyser)
Original value: Power generation (End use: Power generation · Product: Hydrogen)
Original value: Mobility (Product: Hydrogen)
Original value: Hydrogen (Product: Hydrogen)
Original value: 41.98061538461538 kt H2/y (Product: Hydrogen)
Original value: Demonstration
Original value: Steel (End use: Steel · Product: Hydrogen)
Original value: Gas grid injection (End use: Gas grid injection · Product: Synthetic methane)
Published value: 41.98 kt H2/y
- IEA Hydrogen Production Projects 2026
International Energy Agency
Original value: FID/Construction
Original value: DEMO
Original value: Capacity (MWel): 280; Technology: PEM; Product: H2 (Capacity (MWel))
Original value: 2027 (Schedule question: Date online)
Original value: Capacity (kt H2/y): 41.98061538461538 (Capacity (kt H2/y))
Original value: Methane (Product: Methane)
Original value: 280MW (Announced Size)
Original value: PEM electrolyser (Technology: PEM electrolyser)
Original value: Capacity (MWel): 280
Original value: 53846.15384615385 (Capacity (Nm³ H₂/h))
Original value: Hydrogen (Product: Hydrogen)
- Official start of construction of 320-megawatt generation plant in Emden
EWE AG
Original value: green hydrogen (H₂)
Original value: construction started; first green hydrogen planned from end of 2027
Original value: From the end of 2027, the first green hydrogen is to be produced in Emden and delivered to industrial customers.
Original value: construction
- International Energy Agency
International Energy Agency
Original value: DEMO
Original value: PEM electrolyser (Technology: PEM electrolyser)
Original value: 53846.15384615385 (Capacity (Nm³ H₂/h))
Original value: Hydrogen (Product: Hydrogen)
- EWE: Official start of construction of the 320-megawatt generation plant in Emden
EWE AG · As of 2025-11-28
Original value: Official construction start reported, tied to civil/structural contract award
Original value: Under construction
Original value: Emden (Site: Emden)
Original value: end of year 2027
- EWE AG
EWE AG
Original value: From the end of 2027, the first green hydrogen is to be produced in Emden and delivered to industrial customers.
Original value: construction
Original value: Production (Function: Production)
Original value: Emden (Site: Emden)
Original value: construction started; first green hydrogen planned from end of 2027
- Clean Hydrogen Coastline / EWE
Clean Hydrogen Coastline / EWE
Original value: Lower Saxony (Niedersachsen) (Site: Lower Saxony (Niedersachsen))
Original value: Emden (Site: Emden)
- EWE AG (https://www.ewe.com/en/media-center/press-releases/2025/11/official-start-of-construction-of-320-megawatt-generation-plant-in-emdenewe-ag)
EWE AG
Original value: Production (Function: Production)
Original value: Emden (Site: Emden)
Sources (5)
- International Energy Agency
International Energy Agency
Original value: Location
- Official start of construction of 320-megawatt generation plant in Emden
EWE AG
Original value: Location
- EWE: Official start of construction of the 320-megawatt generation plant in Emden
EWE AG · As of 2025-11-28
Original value: Location
- EWE AG
EWE AG
Original value: Location
- IEA Hydrogen Production Projects 2026
International Energy Agency
Original value: Location
Projects in Germany
Major projects: operating and FID first, then by recorded capacity.