GET H2 Nukleus, phase 3

Germany · DE-NI Lower Saxony

Overview

StatusFID / ConstructionRWE Generation SE
Country · regionGermanyRWE Generation SE · DE-NI Lower SaxonyRWE Generation SE
TechnologyAlkaline electrolysis (Sunfire, contracted for the third GET H2 Nukleus construction phase; announced 2024-09-11).
ProductH2International Energy Agency · as of 2026
Capacity100 MWInternational Energy Agency · as of 2026

Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis.

Details

Technology & product

ComponentsElectrolyser (Alkaline)RWE Generation SE
Configuration DetailThird GET H2 Nukleus construction phase: Sunfire to supply a 100-MW alkaline electrolyser; Bilfinger to integrate electrolysis and deliver/install water and hydrogen treatment, compression and control systems (contract announced 2024-09-11; commissioning planned for 2027 in that announcement, not confirmation of installation or operation).
Project GroupGET H2 Nukleus (third construction phase)RWE Generation SE
Project Typehydrogen production facilityRWE Generation SE

Status & timeline

Date online (tracker field)2027 (meaning under review)International Energy Agency · as of 2026

Location & names

Site NameEmsland gas-fired power plant siteRWE Generation SE
Aliasthird 100 MW construction line; third construction phaseRWE Generation SE
Official NameGET H2 NukleusRWE Generation SE

Additional project information

Administrative AreaLingen RWE plantInternational Energy Agency · as of 2026
CountryGermanyInternational Energy Agency · as of 2026
Progress StatusFID / ConstructionInternational Energy Agency · as of 2026
TechnologyALKInternational Energy Agency · as of 2026
Capacity (kt H2/y)16.9 kt H2/yInternational Energy Agency · as of 2026
Capacity (Nm³ H₂/h)21,739 Nm³ H₂/hInternational Energy Agency · as of 2026
Capacity (Announced Size)300 MW total (100 MW phase 3)International Energy Agency · as of 2026

Timeline

  1. Equipment ordered : 2024-09-11RWE Generation SE

Sources & record history

Sources

Field sources

Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.

FieldShown valueOriginal valueSourceDate basisMeaning
NameGET H2 Nukleus, phase 3
View exact valueGET H2 Nukleus, phase 3
IEA Hydrogen Projects dataset——
Site NameEmsland gas-fired power plant site
View exact valueEmsland gas-fired power plant site
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
Administrative AreaDE-NI Lower Saxony
View exact valueDE-NI Lower Saxony
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
Aliasthird 100 MW construction line; third construction phase
View exact value[{"kind":"source_label","name":"third 100 MW construction line"},{"kind":"source_label","name":"third construction phase"}]
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
CountryGermany
View exact valueDEU
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
Official NameGET H2 Nukleus
View exact value[{"lang":"en","name":"GET H2 Nukleus","evidence":["E-01"]}]
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
ComponentsElectrolyser (Alkaline)
View exact value{"kind":"전해조","tech":"알칼라인","tech_raw":"100-MW alkaline electrolyser","component_id":"CMP-1"}
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
Configuration DetailThird GET H2 Nukleus construction phase: Sunfire to supply a 100-MW alkaline electrolyser; Bilfinger to integrate electrolysis and deliver/install water and hydrogen treatment, compression and control systems (contract announced 2024-09-11; commissioning planned for 2027 in that announcement, not confirmation of installation or operation).
View exact valueThird GET H2 Nukleus construction phase: Sunfire to supply a 100-MW alkaline electrolyser; Bilfinger to integrate electrolysis and deliver/install water and hydrogen treatment, compression and control systems (contract announced 2024-09-11; commissioning planned for 2027 in that announcement, not confirmation of installation or operation).
RWE commissions Sunfire and Bilfinger to build third electrolyser plant for GET H2 Nukleus in Lingen—
ProductH2
View exact valueH2
IEA Hydrogen Projects dataset——
Project GroupGET H2 Nukleus (third construction phase)
View exact value{"exists":true,"evidence":["E-01","E-02"],"group_name":"GET H2 Nukleus","phase_name":"third construction phase","phase_order":3}
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
Project Typehydrogen production facility
View exact valuehydrogen_production_facility
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
TechnologyAlkaline electrolysis (Sunfire, contracted for the third GET H2 Nukleus construction phase; announced 2024-09-11).
View exact valueAlkaline electrolysis (Sunfire, contracted for the third GET H2 Nukleus construction phase; announced 2024-09-11).
RWE commissions Sunfire and Bilfinger to build third electrolyser plant for GET H2 Nukleus in Lingen—
Capacity100 MW
View exact value100 MW
IEA Hydrogen Projects dataset——
EventEquipment ordered : 2024-09-11
View exact value{"date":"2024-09-11","tags":{"as_of":"2024-09-11","source":"RWE Generation press release","evidence":["E-07"],"judged_by":"transcription","confidence":"high","accessed_at":"2026-08-17T20:49:35Z"},"ev_type":"EV-08","event_id":"V-02","raw_date_text":"RWE has commissioned Sunfire and Bilfinger to build the third construction phase.","date_precision":"day"}
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
EventDate online : 2027
View exact value{"date":"2027","date_precision":"year","event":"Date online","basis":"iea_hydrogen_projects_raw.csv"}
IEA Hydrogen Projects dataset——
Progress StatusFID / Construction
View exact valueFID/Construction
RWE Generation SE (https://www.rwe.com/en/press/rwe-generation/2024-09-11-rwe-commissions-sunfire-and-bilfinger-to-build-third-electrolyserplant-for-geth2-nukleus/); RWE Generation SE (https://www.rwe.com/presse/rwe-generation/2026-08-04-get-h2-nukleus-nimmt-fahrt-auf/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Older value
Administrative AreaLingen RWE plant
View exact valueLingen RWE plant
IEA Hydrogen Projects dataset——
CountryGermany
View exact valueGermany
IEA Hydrogen Projects dataset——
Progress StatusFID / Construction
View exact valueFID/Construction
IEA Hydrogen Projects dataset——
TechnologyALK
View exact valueALK
IEA Hydrogen Projects dataset——
Capacity (kt H2/y)16.9 kt H2/y
View exact value16.94869565217391 kt H2/y
IEA Hydrogen Projects dataset——
Capacity (Nm³ H₂/h)21,739 Nm³ H₂/h
View exact value21739.130434782608 Nm³ H₂/h
IEA Hydrogen Projects dataset——
Capacity (Announced Size)300 MW total (100 MW phase 3)
View exact value300 MW total (100MW phase 3)
IEA Hydrogen Projects dataset——

Record history

2 current sourced values · 13 older values · Record updated