H2PrismHydrogen intelligenceSubscribe

Castellón refinery green hydrogen phase 1

PEM · Spain

Spain Map: Natural Earth
Capacity
—
Target operation
—
Technology
PEM electrolyser
Country
Spain
Development stage
—

Project details

Site
bp Castellón refinery
Status
Construction completed and commissioning tests begun; commercial operation not established
Sources (3)
  • Tests begin at Spain’s largest green hydrogen facility

    pv magazine Global · As of 2026-07-01

    Original value: bp Castellón refinery (Site: bp Castellón refinery)

    Original value: Construction completed and commissioning tests begun; commercial operation not established

    Original value: PEM electrolyser (Technology: PEM electrolyser)

  • pv magazine Global

    pv magazine Global

    Original value: bp Castellón refinery (Site: bp Castellón refinery)

    Original value: Construction completed and commissioning tests begun; commercial operation not established

    Original value: PEM electrolyser (Technology: PEM electrolyser)

  • Tests begin at Spain’s largest green hydrogen facility

    pv magazine Global

    Original value: Construction completed and commissioning tests begun; commercial operation not established