Moeve La Rábida Energy Park (Huelva) - phase 1 - Andalusian Green Hydrogen Valley ONUBA I Project (Together with THARSIS: LUXIA project)

Spain · ES-AN Andalusia

Overview

StatusConstruction launch celebrated in the 17 September 2026 announcement; commissioning and operation unverified
Country · regionSpainMoeve · as of 2026 · ES-AN AndalusiaMoeve · as of 2026
TechnologyOther ElectrolysisInternational Energy Agency · as of 2026
ProductRenewable hydrogen (Onuba Phase 1 plan)
CapacityPlanned initial 300 MW of electrolysis capacity for Onuba Phase 1 (17 September 2026 announcement)

Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis. “Other Electrolysis” and “Unknown PtX” are recorded classifications, not a specific electrolyzer design or power-to-X route.

Details

Technology & product

Componentselectrolyzer (ALK)Moeve · as of 2026
Configuration DetailALK+PEMInternational Energy Agency · as of 2026
Final UsePlanned renewable fuels for road, aviation and maritime transport, and decarbonisation of other industries (17 September 2026 announcement)
Project GroupAndalusian Green Hydrogen Valley (Onuba)Moeve · as of 2026
Project Typehydrogen production facilityMoeve · as of 2026

Capacity & economics

Production VolumePlanned approximately 45,000 tonnes of renewable hydrogen annually (17 September 2026 announcement)

Status & timeline

Lifecycle StageConstruction launch announced for Onuba Phase 1 (17 September 2026)
Date online (tracker field)2029 (meaning under review)International Energy Agency · as of 2026

Location & names

Site NameMoeve Energy Park, Palos de la Frontera, Huelva, Spain
AliasONUBA Phase 1; Onuba I; Moeve La Rábida Energy Park (Huelva) - phase 1 - Andalusian Green Hydrogen Valley ONUBA I ProjectMoeve · as of 2026
Official NameOnubaMoeve · as of 2026

Additional project information

Administrative AreaHuelvaInternational Energy Agency · as of 2026
CountrySpainInternational Energy Agency · as of 2026
Progress StatusFID / ConstructionInternational Energy Agency · as of 2026
ProductH2International Energy Agency · as of 2026
Capacity (MWel)300 MWelInternational Energy Agency · as of 2026
Capacity (Nm³ H₂/h)66,667 Nm³ H₂/hInternational Energy Agency · as of 2026
Capacity (Announced Size)800 MW(phase 1: 300 MW)International Energy Agency · as of 2026
Capacity (kt H2/y)52 kt H2/yInternational Energy Agency · as of 2026

Timeline

No recorded project events.

Sources & record history

Sources

Field sources

Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.

FieldShown valueOriginal valueSourceDate basisMeaning
NameMoeve La Rábida Energy Park (Huelva) - phase 1 - Andalusian Green Hydrogen Valley ONUBA I Project (Together with THARSIS: LUXIA project)
View exact valueMoeve La Rábida Energy Park (Huelva) - phase 1 - Andalusian Green Hydrogen Valley ONUBA I Project (Together with THARSIS: LUXIA project)
Moeve comenzará la construcción del Valle Andaluz del Hidrógeno VerdeSource dated 2026-01-07Current
Site NameMoeve Energy Park, Palos de la Frontera, Huelva, Spain
View exact valueMoeve Energy Park, Palos de la Frontera, Huelva, Spain
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
Administrative AreaES-AN Andalusia
View exact valueES-AN Andalusia
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
AliasONUBA Phase 1; Onuba I; Moeve La Rábida Energy Park (Huelva) - phase 1 - Andalusian Green Hydrogen Valley ONUBA I Project
View exact value[{"kind":"source_label","name":"ONUBA Phase 1"},{"kind":"source_label","name":"Onuba I"},{"kind":"source_label","name":"Moeve La Rábida Energy Park (Huelva) - phase 1 - Andalusian Green Hydrogen Valley ONUBA I Project"}]
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
CountrySpain
View exact valueESP
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
Official NameOnuba
View exact value[{"lang":"en","name":"Onuba","evidence":["E-01"]}]
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
Componentselectrolyzer (ALK)
View exact value{"kind":"electrolyzer","tech":"ALK","tech_raw":"alkaline water electrolysis technology","component_id":"CMP-1"}
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
Configuration DetailALK+PEM
View exact valueALK+PEM
IEA Hydrogen Projects dataset——
Final UsePlanned renewable fuels for road, aviation and maritime transport, and decarbonisation of other industries (17 September 2026 announcement)
View exact valuePlanned renewable fuels for road, aviation and maritime transport, and decarbonisation of other industries (17 September 2026 announcement)
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
ProductRenewable hydrogen (Onuba Phase 1 plan)
View exact valueRenewable hydrogen (Onuba Phase 1 plan)
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
Project GroupAndalusian Green Hydrogen Valley (Onuba)
View exact value{"exists":true,"evidence":["E-01","E-03"],"group_name":"Andalusian Green Hydrogen Valley","phase_name":"Onuba","phase_order":1}
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
Project Typehydrogen production facility
View exact valuehydrogen_production_facility
Moeve (https://www.moeveglobal.com/en/press/moeve-investment-andalusian-green-hydrogen-valley-onuba-huelva); Moeve (https://www.moeveglobal.com/en/press/moeve-thyssenkrupp-nucera-electrolyzers-green-hydrogen-onuba); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); Moeve (https://www.moeveglobal.com/en/businesses/commercial-clean-energies/green-hydrogen/andalusian-valley/financing-and-planning); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-03-02Older value (2026)
TechnologyOther Electrolysis
View exact valueOther Electrolysis
IEA Hydrogen Projects dataset——
CapacityPlanned initial 300 MW of electrolysis capacity for Onuba Phase 1 (17 September 2026 announcement)
View exact valuePlanned initial 300 MW of electrolysis capacity for Onuba Phase 1 (17 September 2026 announcement)
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
Production VolumePlanned approximately 45,000 tonnes of renewable hydrogen annually (17 September 2026 announcement)
View exact valuePlanned approximately 45,000 tonnes of renewable hydrogen annually (17 September 2026 announcement)
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
EventDate online : 2029
View exact value{"date":"2029","date_precision":"year","event":"Date online","basis":"iea_hydrogen_projects_raw.csv"}
IEA Hydrogen Projects dataset——
Lifecycle StageConstruction launch announced for Onuba Phase 1 (17 September 2026)
View exact valueConstruction launch announced for Onuba Phase 1 (17 September 2026)
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
Progress StatusConstruction launch celebrated in the 17 September 2026 announcement; commissioning and operation unverified
View exact valueConstruction launch celebrated in the 17 September 2026 announcement; commissioning and operation unverified
Moeve launches construction of the first phase of the Andalusian Green Hydrogen Valley——
Administrative AreaHuelva
View exact valueHuelva
IEA Hydrogen Projects dataset——
CountrySpain
View exact valueSpain
IEA Hydrogen Projects dataset——
Progress StatusFID / Construction
View exact valueFID/Construction
IEA Hydrogen Projects dataset——
ProductH2
View exact valueH2
IEA Hydrogen Projects dataset——
Capacity (MWel)300 MWel
View exact value300 MWel
IEA Hydrogen Projects dataset——
Capacity (Nm³ H₂/h)66,667 Nm³ H₂/h
View exact value66666.66666666667 Nm³ H₂/h
IEA Hydrogen Projects dataset——
Capacity (Announced Size)800 MW(phase 1: 300 MW)
View exact value800 MW(phase 1: 300 MW)
IEA Hydrogen Projects dataset——
Capacity (kt H2/y)52 kt H2/y
View exact value51.976 kt H2/y
IEA Hydrogen Projects dataset——

Record history

7 current sourced values · 10 older values · Record updated