313 MW · Electrolysis · Canada

Feasibility

Canada Map: Natural Earth
Capacity
313 MW
Target operation
2028
Technology
Electrolysis
Country
Canada
Development stage
Feasibility

Target operation

2028Target operation
  1. 2026
  2. 2027
  3. 2028
  4. 2029
  5. 2030

Target year as recorded for this project. The axis does not imply stage history.

Country scale

#15 by recorded MW among 48 projects with capacity recorded in this country.

  1. Toqlukuti'k Wind and H2 Project2,500 MW
  2. Point Tupper green hydrogen project, phase 22,402 MW
  3. SAF Production Co-located at Renewable Diesel & Renewable Hydrogen Complex313 MW

All stages are included. Capacity does not describe current production.

Project details

Product
Synthetic diesel and gasoline · Synthetic fuels
Site
Prince Rupert
Production capacity
54.2 ktpa
Sources (3)
  • IEA Hydrogen Production Projects 2026 (preserved CSV edition, received 2026-10-24)

    International Energy Agency · As of 2026-06-18

    Original value: Feasibility

    Original value: Synthetic diesel and gasoline (Product: Synthetic diesel and gasoline)

    Original value: Biofuels (Product: Hydrogen)

    Original value: Other electrolysis

    Original value: Prince Rupert (Site: Prince Rupert)

    Original value: 2028

    Original value: 54.16441597414589 kt H2/y (Product: Hydrogen)

    Original value: 312.63130660773754 MW

    Published value: 54.16 kt H2/y

    Published value: 312.6 MW

  • IEA Hydrogen Production Projects 2026

    International Energy Agency

    Original value: Feasibility study

    Original value: 69473.62369060835 (Capacity (Nm³ H₂/h))

    Original value: 2028 (Schedule question: Date online)

    Original value: Water electrolysis (Technology: Water electrolysis)

    Original value: 54.16441597414589 (Capacity (kt H2/y))

    Original value: 6500 bpd of SAF (Announced Size)

    Original value: Synthetic fuels (Product: Synthetic fuels)

    Original value: Capacity (MWel): 312.63130660773754

  • International Energy Agency

    International Energy Agency

    Original value: 69473.62369060835 (Capacity (Nm³ H₂/h))

    Original value: Water electrolysis (Technology: Water electrolysis)

    Original value: 54.16441597414589 (Capacity (kt H2/y))

Projects in Canada

Major projects: operating and FID first, then by recorded capacity.

All projects in this country