5 MW · Alkaline · Netherlands

Feasibility

Netherlands Map: Natural Earth
Capacity
5 MW
Target operation
—
Technology
Alkaline
Country
Netherlands
Development stage
Feasibility

Also known as Electrolysis Technology for Hydrogen and Oxygen production in Rotterdam (e-THOR) · e-THOR

Country scale

#56 by recorded MW among 82 projects with capacity recorded in this country.

  1. NortH2, phase 23,000 MW
  2. e-SAF hub in the Port of Rotterdam2,274 MW
  3. Publiek Eindrapport: Electrolysis Technology for Hydrogen and Oxygen production in Rotterdam (e-THOR), ref RVO TESN1190115 MW

All stages are included. Capacity does not describe current production.

Project details

Scale
Research or pilot
Function
Production
Product
Methanol
Allocated power supply
4.7 MW
Sources (13)
  • International Energy Agency

    International Energy Agency

    Original value: Water electrolysis (Technology: Water electrolysis)

  • IEA Hydrogen Production Projects 2026

    International Energy Agency

    Original value: Water electrolysis (Technology: Water electrolysis)

    Original value: Methanol (Product: Methanol)

    Original value: 5MW (Announced Size)

  • Topsector Energie

    Topsector Energie

    Original value: initial investigation completed; later implementation status not established

    Original value: This project will result in the following three reports as outcome

  • Electrolysis Technology for H2 and O2 production in Rotterdam

    Topsector Energie

    Original value: initial investigation completed; later implementation status not established

    Original value: This project will result in the following three reports as outcome

  • e-THOR consortium / Topsector Energie

    e-THOR consortium / Topsector Energie

    Original value: AVR electricity; flexible operation/grid-services scenarios considered (Process section: flexible electrolysis operation)

    Original value: Production (Function: Production)

    Original value: initial feasibility investigation / study; no construction or operation established

    Original value: 4.7 MW (Supply: AVR in-house supply to alkaline electrolyzer)

  • Publiek Eindrapport: Electrolysis Technology for Hydrogen and Oxygen production in Rotterdam (e-THOR), ref RVO TESN119011

    e-THOR consortium / Topsector Energie

    Original value: AVR electricity; flexible operation/grid-services scenarios considered (Process section: flexible electrolysis operation)

    Original value: Production (Function: Production)

    Original value: Alkaline electrolyser (Technology: Alkaline electrolyser)

    Original value: initial feasibility investigation / study; no construction or operation established

    Original value: water (Feedstock: water)

    Original value: 4.7 MW (Supply: AVR in-house supply to alkaline electrolyzer)

  • Electrolysis Technology for H2 and O2 production in Rotterdam

    Topsector Energie / RVO

    Original value: Research or pilot

    Original value: hydrogen for Rotterdam harbor industrial cluster

    Original value: TSE grant; registry amount €42,661.00

  • Topsector Energie / RVO

    Topsector Energie / RVO

    Original value: Research or pilot

  • IEA Hydrogen Production Projects 2026 (preserved CSV edition, received 2026-10-24)

    International Energy Agency · As of 2026-06-18

    Original value: Feasibility

    Original value: Methanol (Product: Methanol)

    Original value: Methanol (Product: Hydrogen)

    Original value: 5 MW

  • e-THOR: closing chains with an electrolyzer

    SmartPort

    Original value: Rotterdam (Site: Rotterdam)

    Original value: AVR (Site: AVR)

  • SmartPort

    SmartPort

    Original value: Rotterdam (Site: Rotterdam)

    Original value: AVR (Site: AVR)

  • Publiek Eindrapport Electrolysis Technology for Hydrogen and Oxygen production in Rotterdam (e-THOR)

    AVR, Tronox, TNO and Deltalinqs

    Original value: Following the results of this study AVR and Tronox have first of all obtained a much better understanding of the business case mechanisms

  • AVR, Tronox, TNO and Deltalinqs

    AVR, Tronox, TNO and Deltalinqs

    Original value: Following the results of this study AVR and Tronox have first of all obtained a much better understanding of the business case mechanisms

Projects in Netherlands

Major projects: operating and FID first, then by recorded capacity.