- Capacity
- 10 MW
- Target operation
- —
- Technology
- Electrolysis
- Country
- Australia
- Development stage
- Concept
Country scale
#89 by recorded MW among 122 projects with capacity recorded in this country.
- Western Green Energy Hub (WGEH), final phase42,366 MW
- Australian Renewable Energy Hub, first phase15,357 MW
- BlueScope’s Port Kembla Steelworks, Illawarra10 MW
All stages are included. Capacity does not describe current production.
Project details
- Electricity source
- Renewable
- Site
- BlueScope Port Kembla Steelworks
- Production capacity
- 1.73 ktpa
Sources (3)
- IEA Hydrogen Production Projects 2026
International Energy Agency
Original value: Concept
Original value: Hydrogen (Product: Hydrogen)
Original value: Capacity (MWel): 10
Original value: Water electrolysis (Technology: Water electrolysis)
Original value: 10MW (Announced Size)
Original value: Capacity (MWel): 10; Technology: Other Electrolysis; Product: H2 (Capacity (MWel))
Original value: 2222.222222222222 (Capacity (Nm³ H₂/h))
- IEA Hydrogen Production Projects 2026 (preserved CSV edition, received 2026-10-24)
International Energy Agency · As of 2026-06-18
Original value: Concept
Original value: Renewable (Electricity source: Renewable)
Original value: Steel (End use: Steel · Product: Hydrogen)
Original value: 10 MW
Original value: BlueScope Port Kembla Steelworks (Site: BlueScope Port Kembla Steelworks)
Original value: 1.7325333333333333 kt H2/y (Product: Hydrogen)
Original value: Other Electrolysis
Original value: Hydrogen (Product: Hydrogen)
Published value: 1.733 kt H2/y
- International Energy Agency
International Energy Agency
Original value: Hydrogen (Product: Hydrogen)
Original value: Water electrolysis (Technology: Water electrolysis)
Original value: 2222.222222222222 (Capacity (Nm³ H₂/h))
Sources (2)
- IEA Hydrogen Production Projects 2026
International Energy Agency
Original value: Location
- IEA Hydrogen Production Projects 2026 (preserved CSV edition, received 2026-10-24)
International Energy Agency · As of 2026-06-18
Original value: Location
Projects in Australia
Major projects: operating and FID first, then by recorded capacity.