Analysis · 4 min read
EU RFNBO electricity rules: direct lines and grid power
Regulation 2023/1184 offers different routes for counting electricity as fully renewable. Identify the route before applying additionality, timing and location tests.
Choose the electricity route before checking the tests
Commission Delegated Regulation (EU) 2023/1184 sets conditions for counting electricity used in renewable fuels of non-biological origin (RFNBOs) as fully renewable. Article 3 covers direct connections. Article 4 provides routes for electricity taken from the grid. This article uses the consolidated text dated 10 June 2024.
Under Article 3, renewable generation must be connected by a direct line or located within the same installation, and meet the specified 36-month start-date condition. It must be disconnected from the grid, or smart metering must demonstrate that no grid electricity was used to produce the RFNBO. Any grid electricity counted as fully renewable also needs an Article 4 route.
A direct connection therefore needs evidence about the actual installation, dates and electricity flows. The commercial name of a power agreement or an annual renewable-energy certificate total does not establish all of those conditions.
Sources
- [1] European Commission / EUR-Lex: Commission Delegated Regulation (EU) 2023/1184, consolidated version of 10 June 2024
Last confirmed: 16 Nov 2026
The grid routes have different conditions
Article 4 distinguishes a high-renewables bidding zone, a low-emissions bidding zone, a redispatch route and a route using the additionality, temporal and geographical conditions. Do not apply the same checklist to every route without reading its conditions.
For the above-90% route, the renewable-electricity share refers to the previous calendar year. The operating-hour cap is the number of hours in the relevant calendar year multiplied by the qualifying share, using the calculation in Article 4(1). It is not a fixed 8,760-hour multiplier. A zone passing the threshold retains that status for the following five calendar years.
Article 4(2) applies below 18 gCO₂e/MJ of grid electricity. It requires renewable power purchase agreements covering at least the electricity quantity counted as fully renewable, actual production of that renewable electricity, and the Article 6 and 7 tests. It does not invoke Article 5 additionality. Once the zone falls below the threshold, the regulation continues to treat it as below that level for the next five calendar years.
Article 4 routes: read the conditions for the electricity being counted
| Route | Key evidence or condition |
|---|---|
| Above 90% renewable electricity | Prior-year bidding-zone share and the Article 4(1) operating-hour cap |
| Below 18 gCO₂e/MJ | Renewable power purchase agreement and temporal and geographical correlation |
| Redispatch | National transmission-operator evidence that, during the imbalance settlement period, renewable installations were redispatched downwards under Article 13 of Regulation (EU) 2019/943 and consumption reduced the redispatch need by a corresponding amount |
| Article 4(4) | Additionality, temporal correlation and geographical correlation under Articles 5, 6 and 7 |
Sources
- [1] European Commission / EUR-Lex: Commission Delegated Regulation (EU) 2023/1184, consolidated version of 10 June 2024
Last confirmed: 16 Nov 2026
Timing and location require their own evidence
For Article 4(4), Article 5 includes a renewable-generation start date no earlier than 36 months before the fuel installation and a test concerning operating or investment aid. It also lists exceptions, including certain land and grid-connection support. A blanket statement that all public support disqualifies the electricity would omit those exceptions.
Article 6 permits monthly temporal correlation through 31 December 2029. From 1 January 2030, the renewable fuel must be produced in the same one-hour period as the renewable electricity under the power purchase agreement. Member States may apply the hourly rules from 1 July 2027 following notification to the Commission. Article 6 also treats temporal correlation as met when the renewable fuel is produced in a one-hour period in which the electricity clearing price from single day-ahead market coupling in the bidding zone is EUR 20 per MWh or lower, or lower than 0.36 times the price of an allowance to emit one tonne of carbon dioxide equivalent during the relevant period.
Article 7 allows the same bidding zone, an interconnected zone meeting its day-ahead price comparison, or an offshore zone interconnected with the electrolyser zone. In the interconnected-zone route, the renewable-generation zone price must be equal to or higher than the fuel-production zone price in the relevant period. The rule does not establish that electricity physically flowed toward a particular electrolyser.
The regulation also permits additional national location criteria for compatibility with hydrogen and electricity network planning, subject to its stated limits. A cross-border purchase proposal therefore needs more than a country-level renewable-generation figure.
Sources
- [1] European Commission / EUR-Lex: Commission Delegated Regulation (EU) 2023/1184, consolidated version of 10 June 2024
Last confirmed: 16 Nov 2026
The transition waives specific tests, not the whole framework
Article 11 postpones the application of Article 5(a) and 5(b) until 1 January 2038 for fuel installations that come into operation before 1 January 2028. The exemption does not apply to capacity added after 1 January 2028. It covers both the start-date and aid tests in Article 5, not temporal or geographical correlation.
For a procurement review, record which route covers each electricity quantity and which evidence supports it. Check installation dates, metered flows, the applicable agreement, bidding-zone conditions and relevant time periods. Keep planned operation separate from evidence that an installation has come into operation.
These are electricity-sourcing rules. A complete RFNBO assessment also needs the other applicable product, emissions and certification requirements. Do not reuse a greenhouse-gas threshold or a project-utilisation assumption as a substitute for this electricity evidence.
Sources
- [1] European Commission / EUR-Lex: Commission Delegated Regulation (EU) 2023/1184, consolidated version of 10 June 2024
Last confirmed: 16 Nov 2026
Related analyses
Explore related records
Research method
Research and writing were AI-assisted and reviewed before publication.