H2Prism
Hydrogen calculators & data

Elektrolyse Ostfriesland / Clean Hydrogen Coastline – Electrolysis East Frisia

Germany · Lower Saxony (Niedersachsen)

Elektrolyse Ostfriesland / Clean Hydrogen Coastline – Electrolysis East Frisia is a hydrogen project in Lower Saxony (Niedersachsen), Germany using electrolysis; recorded capacity: 320 (unit not recorded).

Overview

Statusconstruction started; first green hydrogen planned from end of 2027
Country · regionGermany · Lower Saxony (Niedersachsen)
Technologyelectrolysis
Productgreen hydrogen (H₂)
Capacity320 (unit not recorded)

Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis.

Details

Technology & product

Componentselectrolyser, connection to electricity grid/substation, planned hydrogen core-network connection
Final Useindustry, energy sector, heavy-duty transport
Power Sourcerenewable energy
Project GroupClean Hydrogen Coastline

Capacity & economics

Production Volumeapproximately 1,000,000,000 kWh per year (approximately 1 TWh)

Status & timeline

Lifecycle Stageconstruction
Eventofficial start of construction
Date online (tracker field)2015 (meaning under review)International Energy Agency · as of 2026

Location & names

Site NameEmden

Additional project information

Progress StatusDemoInternational Energy Agency · as of 2026
ProductCH4International Energy Agency · as of 2026
TechnologyPEMInternational Energy Agency · as of 2026

Timeline

No recorded project events.

Sources & record history

Sources

Field sources

Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.

FieldShown valueOriginal valueSourceDate basisMeaning
NameElektrolyse Ostfriesland / Clean Hydrogen Coastline – Electrolysis East Frisia
View exact valueElektrolyse Ostfriesland / Clean Hydrogen Coastline – Electrolysis East Frisia
Official start of construction of 320-megawatt generation plant in Emden—
Site NameEmden
View exact valueEmden
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Administrative AreaLower Saxony (Niedersachsen)
View exact valueLower Saxony (Niedersachsen)
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
CountryGermany
View exact valueGermany
Official start of construction of 320-megawatt generation plant in Emden—
Componentselectrolyser, connection to electricity grid/substation, planned hydrogen core-network connection
View exact value["electrolyser","connection to electricity grid/substation","planned hydrogen core-network connection"]
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Final Useindustry, energy sector, heavy-duty transport
View exact value["industry","energy sector","heavy-duty transport"]
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Power Sourcerenewable energy
View exact valuerenewable energy
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Productgreen hydrogen (H₂)
View exact valuegreen hydrogen (H₂)
Official start of construction of 320-megawatt generation plant in Emden—
Project GroupClean Hydrogen Coastline
View exact valueClean Hydrogen Coastline
Official start of construction of 320-megawatt generation plant in Emden—
Technologyelectrolysis
View exact valueelectrolysis
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Capacity320 (unit not recorded)
View exact value320
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Production Volumeapproximately 1,000,000,000 kWh per year (approximately 1 TWh)
View exact valueapproximately 1,000,000,000 kWh per year (approximately 1 TWh)
Elektrolyseur Emden – Wasserstoffwirtschaft in Ostfriesland—
Eventofficial start of construction
View exact valueofficial start of construction
Official start of construction of 320-megawatt generation plant in Emden—
EventDate online : 2015
View exact value{"date":"2015","date_precision":"year","event":"Date online","basis":"iea_hydrogen_projects_raw.csv"}
IEA Hydrogen Projects dataset——
Lifecycle Stageconstruction
View exact valueconstruction
Official start of construction of 320-megawatt generation plant in Emden—
Progress Statusconstruction started; first green hydrogen planned from end of 2027
View exact valueconstruction started; first green hydrogen planned from end of 2027
Official start of construction of 320-megawatt generation plant in Emden—
Progress StatusDemo
View exact valueDEMO
IEA Hydrogen Projects dataset——
ProductCH4
View exact valueCH4
IEA Hydrogen Projects dataset——
TechnologyPEM
View exact valuePEM
IEA Hydrogen Projects dataset——

Record history

14 current sourced values · 1 older value · Record updated