Atome - La Villeta

Paraguay

Overview

StatusFID / ConstructionATOME PLC via RNS · as of 2026
Country · regionParaguayInternational Finance Corporation · as of 2025
TechnologySungrow alkaline electrolysis (planned; announced 22 May 2026)
ProductAmmoniaInternational Energy Agency · as of 2026
Capacity145 MWInternational Energy Agency · as of 2026

Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis.

Details

Technology & product

ComponentsElectrolyser (Alkaline)International Finance Corporation · as of 2025green calcium ammonium nitrate fertilizer plantInternational Finance Corporation · as of 2025
Final UsePlanned calcium ammonium nitrate (CAN) fertiliser manufacture (announced 22 May 2026)
Power SourcePlanned 100% renewable baseload hydropower from Itaipu Dam (22 May 2026 design)
Project Typehydrogen production facilityInternational Finance Corporation · as of 2025

Capacity & economics

Purchase Agreement DetailsTerm: 10-year; Buyer: Yara International; Binding: binding; Product: green fertiliser productionATOME PLC via RNS · as of 2026
Total Capex665 USD million debt and equity funding for the project (announced)ATOME PLC

Status & timeline

EventATOME reported notice to terminate the 2022 PPA effective end-2026 and continued negotiations with ANDE and Government (1 October 2026)
Date online (tracker field)2028 (meaning under review)International Energy Agency · as of 2026

Location & names

Site NameVilletaInternational Finance Corporation · as of 2025
AliasATOME - La Villeta; Villeta Green Fertilizer ProjectInternational Finance Corporation · as of 2025
Official NameVilleta ProjectInternational Finance Corporation · as of 2025

Additional project information

Administrative AreaVilleta, hydroelectric power from the Itaipu damInternational Energy Agency · as of 2026
CountryParaguayInternational Energy Agency · as of 2026
Progress StatusFID / ConstructionInternational Energy Agency · as of 2026
TechnologyALKInternational Energy Agency · as of 2026
Capacity (Nm³ H₂/h)31,522 Nm³ H₂/hInternational Energy Agency · as of 2026
Capacity (kt H2/y)24.6 kt H2/yInternational Energy Agency · as of 2026
Capacity (Announced Size)145 MWInternational Energy Agency · as of 2026

Timeline

  1. Investment agreement signed : 2025-04ATOME PLC
  2. Final investment decision (FID) : 2026-05-13ATOME PLC via RNS · as of 2026

Sources & record history

Sources

Field sources

Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.

FieldShown valueOriginal valueSourceDate basisMeaning
NameAtome - La Villeta
View exact valueAtome - La Villeta
IEA Hydrogen Projects dataset——
Site NameVilleta
View exact valueVilleta
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
AliasATOME - La Villeta; Villeta Green Fertilizer Project
View exact value[{"kind":"source_label","name":"ATOME - La Villeta"},{"kind":"other_spelling","name":"Villeta Green Fertilizer Project"}]
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
CountryParaguay
View exact valuePRY
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
Official NameVilleta Project
View exact value[{"lang":"en","name":"Villeta Project","evidence":["E-03"]}]
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
ComponentsElectrolyser (Alkaline)
View exact value{"kind":"전해조","tech":"알칼라인","tech_raw":"pressurized alkaline water electrolysis system","component_id":"CMP-1"}
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
Componentsgreen calcium ammonium nitrate fertilizer plant
View exact value{"kind":"기타","tech":"기타","tech_raw":"green calcium ammonium nitrate fertilizer plant","component_id":"CMP-2"}
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
Final UsePlanned calcium ammonium nitrate (CAN) fertiliser manufacture (announced 22 May 2026)
View exact valuePlanned calcium ammonium nitrate (CAN) fertiliser manufacture (announced 22 May 2026)
Sungrow Selected as Villeta Electrolyser Supplier——
Power SourcePlanned 100% renewable baseload hydropower from Itaipu Dam (22 May 2026 design)
View exact valuePlanned 100% renewable baseload hydropower from Itaipu Dam (22 May 2026 design)
Sungrow Selected as Villeta Electrolyser Supplier——
ProductAmmonia
View exact valueAmmonia
IEA Hydrogen Projects dataset——
Project Typehydrogen production facility
View exact valuehydrogen_production_facility
International Finance Corporation (https://disclosures.ifc.org/project-detail/ESRS/47553/atome-villeta-green-fertilizer); ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); International Finance Corporation (https://disclosures.ifc.org/project-detail/SII/47553/atome-villeta-green-fertilizer); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2025-06-09Older value (2025)
TechnologySungrow alkaline electrolysis (planned; announced 22 May 2026)
View exact valueSungrow alkaline electrolysis (planned; announced 22 May 2026)
Sungrow Selected as Villeta Electrolyser Supplier——
Capacity145 MW
View exact value145 MW
IEA Hydrogen Projects dataset——
Purchase Agreement DetailsTerm: 10-year; Buyer: Yara International; Binding: binding; Product: green fertiliser production
View exact value{"term":"10-year","buyer":"Yara International","binding":"구속","product":"green fertiliser production","raw_text":"a 10-year Definitive Offtake Agreement signed with Yara International ... for offtake of all of Villeta's green fertiliser production"}
ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-05-13Older value (2026)
Total Capex665 USD million debt and equity funding for the project (announced)
View exact value{"amount":665,"nature":"발표","of_what":"debt and equity funding for the project","currency":"USD million"}
ATOME PLC (https://www.atomeplc.com/projects/villeta/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Publication date unknown · accessed 2026-08-17Older value
EventFinal investment decision (FID) : 2026-05-13
View exact value{"date":"2026-05-13","tags":{"as_of":"2026-05-13","source":"ATOME RNS, Results of General Meeting - Unconditional FID","evidence":["E-03"],"judged_by":"worker_review","confidence":"high","accessed_at":"2026-08-17T22:56:54Z"},"ev_type":"EV-05","event_id":"V-01","raw_date_text":"13 May 2026","date_precision":"day"}
ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-05-13Older value (2026)
EventInvestment agreement signed : 2025-04
View exact value{"date":"2025-04","tags":{"as_of":"2025-04","source":"ATOME Villeta project page","evidence":["E-01"],"judged_by":"transcription","confidence":"high","accessed_at":"2026-08-17T22:56:54Z"},"ev_type":"EV-04","event_id":"V-02","raw_date_text":"In April 2025, ATOME signed the EPC Contract with CASALE","date_precision":"month"}
ATOME PLC (https://www.atomeplc.com/projects/villeta/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Publication date unknown · accessed 2026-08-17Older value
EventATOME reported notice to terminate the 2022 PPA effective end-2026 and continued negotiations with ANDE and Government (1 October 2026)
View exact valueATOME reported notice to terminate the 2022 PPA effective end-2026 and continued negotiations with ANDE and Government (1 October 2026)
Villeta UpdateSource dated 2026-10-01Current
EventDate online : 2028
View exact value{"date":"2028","date_precision":"year","event":"Date online","basis":"iea_hydrogen_projects_raw.csv"}
IEA Hydrogen Projects dataset——
Progress StatusFID / Construction
View exact valueFID/Construction
ATOME PLC via RNS (https://www.lse.co.uk/rns/ATOM/results-of-general-meeting-unconditional-fid-ue5wggpzal9vy81.html); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200)Source dated 2026-05-13Older value (2026)
Administrative AreaVilleta, hydroelectric power from the Itaipu dam
View exact valueVilleta, hydroelectric power from the Itaipu dam
IEA Hydrogen Projects dataset——
CountryParaguay
View exact valueParaguay
IEA Hydrogen Projects dataset——
Progress StatusFID / Construction
View exact valueFID/Construction
IEA Hydrogen Projects dataset——
TechnologyALK
View exact valueALK
IEA Hydrogen Projects dataset——
Capacity (Nm³ H₂/h)31,522 Nm³ H₂/h
View exact value31521.739130434784 Nm³ H₂/h
IEA Hydrogen Projects dataset——
Capacity (kt H2/y)24.6 kt H2/y
View exact value24.57560869565217 kt H2/y
IEA Hydrogen Projects dataset——
Capacity (Announced Size)145 MW
View exact value145MW
IEA Hydrogen Projects dataset——

Record history

4 current sourced values · 15 older values · Record updated

H2Prism separates published values from estimates. Check the linked source before you use a value. · Back to Hydrogen projects

Records are compiled with AI assistance. Original source links are shown when available.