Hydrogen Production Delivery Roadmap

Hydrogen Production Delivery Roadmap policy record on H2Prism, with its status, summary, checked official source, and record date.

The official link is checked before a policy can appear here.

8 sourced values · 0 earlier records

JurisdictionGBR
Legal statusin_force
Instrumenttarget
Effective2024-06-01

Policy details

SummaryA government delivery roadmap (published June 2024) setting out the sequencing of policy interventions, allocation rounds, and deployment milestones required to reach the 10 GW 2030 ambition, including CCUS-enabled and electrolytic tracks with specific capacity milestones and annual round cadence.
Key thresholdsTarget: up to 10 GW low carbon hydrogen production capacity by 2030 (at least 5 GW electrolytic, up to 4 GW CCUS-enabled, remainder from alternative technologies). Interim: up to 1 GW electrolytic and 1 GW CCUS-enabled operational or under construction by 2025 (milestone under review). Annual allocation rounds from 2025 to 2030; HAR3 and HAR4 to target up to 1.5 GW combined. Hydrogen to power applications identified as a priority use case in Clean Power 2030 mission context.
Support valueNo direct financial support — sets policy sequencing; financial support delivered through HPBM/HAR and NZHF.
Practical implicationThe roadmap signals that annual HAR rounds will continue through 2030, giving developers a clear forward window to plan pipeline projects, but the 2025 interim milestone slippage (only 125 MW awarded in HAR1 vs 250 MW targeted) underscores that policy ambition does not guarantee pipeline readiness or award rates.

Official source

SourcePublisherChecked
Open official source ↗www.gov.uk2026-08-31T17:47:03Z