RWE and TotalEnergies: Lingen hydrogen agreed for Leuna from 2030
The agreement calls for around 30,000 tonnes a year from 2030. Hydrogen reaching Marl is a separate milestone.
The agreement and its delivery date
RWE and TotalEnergies announced a long-term green hydrogen agreement on 12 March 2025. RWE said TotalEnergies would buy around 30,000 metric tonnes a year for its Leuna refinery from 2030 through 2044. The announcement describes a 15-year agreement and identifies RWE’s planned 300 MW plant in Lingen as the production source.
The quantity is an annual contracted amount, not evidence of delivery to Leuna. RWE linked the supply relationship to Germany’s planned hydrogen core network. Its announcement does not provide the complete commercial terms, a detailed route or a transport tariff.
A future supply agreement and hydrogen received at a refinery are different milestones. Production tests equipment; transport establishes whether hydrogen can reach an industrial destination. The Leuna start remains a future contract milestone in the sources reviewed here.
Sources
- [1] RWE: RWE and TotalEnergies agree long-term offtake agreement for green hydrogen
As of: 12 Mar 2025
Last confirmed: 16 Nov 2026
What RWE reported at Lingen
On 4 August 2026, RWE reported that initial renewable hydrogen produced during commissioning of two 100 MW electrolysis plants in Lingen had reached Marl Chemical Park through a network of around 120 km. RWE said it was available for industrial processes there and that the plants would be prepared for commercial operation. This report concerns Marl, not delivery under the Leuna agreement.
In that update RWE said it was commissioning 200 MW at Lingen by the end of 2026 and scheduled the full 300 MW plant to operate from 2027. Those are company plans from August 2026, not proof that the entire plant has entered commercial operation.
The equipment phases differ. The 11 September 2024 release says the first two 100 MW electrolyzers had already been ordered from Linde Engineering and ITM Power in 2022. Sunfire was to supply an alkaline electrolyzer for the third 100 MW phase, with Bilfinger responsible for integration and ancillary systems.
Sources
- [2] RWE: GET H2 Nukleus gains momentum: First hydrogen from Lingen reaches Marl
As of: 4 Aug 2026
Last confirmed: 16 Nov 2026
- [3] RWE: RWE commissions Sunfire and Bilfinger to build third electrolyser plant for GET H2 Nukleus in Lingen
As of: 11 Sep 2024
Last confirmed: 16 Nov 2026
Network and storage milestones
In March 2025 RWE said the German hydrogen core network would facilitate the Lingen to Leuna supply relationship. It described a network of more than 9,000 km to be phased into operation between 2025 and 2032 by repurposing existing gas pipelines and building new pipeline sections. In the same release, TotalEnergies’ chief executive said the contract will be made possible by the completion of the hydrogen backbone by German authorities. The release does not specify which network sections must be in service before the first delivery to Leuna.
RWE also said it would use booked capacity at Gronau-Epe hydrogen storage to supply hydrogen during periods with little sun and wind. In August 2026 it said OGE and Nowega had completed the Heek to Epe connection at the end of 2025. Filling of the first commercial cavern is to begin at the end of 2026, and the facility is scheduled to start operating in mid-2027. A completed connection, a filling date and a scheduled operating start do not prove the storage is already in commercial operation.
A long-term supply arrangement brings production, relevant transport, storage if used, and customer readiness together. Progress on one component does not settle the status of all the others.
Sources
- [1] RWE: RWE and TotalEnergies agree long-term offtake agreement for green hydrogen
As of: 12 Mar 2025
Last confirmed: 16 Nov 2026
- [2] RWE: GET H2 Nukleus gains momentum: First hydrogen from Lingen reaches Marl
As of: 4 Aug 2026
Last confirmed: 16 Nov 2026
What to watch
Look for dated updates from the parties and infrastructure operators on commercial operation at Lingen, the connection to Leuna and the start of contracted deliveries. A storage update should distinguish filling, commissioning and commercial operation. A network announcement should identify the relevant section and date.
Also look for disclosed delivery conditions and changes to the contracted schedule. The 2025 announcement gives the quantity and term, but does not establish the price, every risk allocation or a guarantee of continuous delivery.
Sources
- [1] RWE: RWE and TotalEnergies agree long-term offtake agreement for green hydrogen
As of: 12 Mar 2025
Last confirmed: 16 Nov 2026