45V hydrogen credit: the 2028 construction deadline and the 10-year period
The construction cutoff and the production-credit period answer different questions. Read both before putting a 45V assumption into a hydrogen project model.
Begin with the construction cutoff
The IRS instructions for Form 7210 for tax year 2025 explain the effect of Public Law 119-21: Section 45V is unavailable to facilities beginning construction after 2027. Their definition of a qualified clean hydrogen production facility requires construction to begin before 1 January 2028.
That condition concerns the beginning of construction. The credit period has a different starting event: the date the facility is originally placed in service. The instructions describe a 10-year period of qualified clean hydrogen production beginning on that date.
A project schedule should therefore keep a construction-start date and a placed-in-service date in separate fields. Evidence for one does not establish the other. An announcement of investment, an intended commissioning year or a planned supply agreement does not, by itself, document how the taxpayer satisfies the construction rule.
Sources
- [1] Internal Revenue Service: Instructions for Form 7210 (2025)
Last confirmed: 16 Nov 2026
Establish the event behind each date
The instructions identify two ways to establish that construction begins: physical work of a significant nature, or paying or incurring at least 5% of the facility's total cost under the Five Percent Safe Harbor. Those are the named routes; applying either route requires the relevant requirements and project evidence.
For a screening discussion, ask which route the project uses and what documents support it. Keep an intended date separate from evidence of the event. This article does not decide whether particular expenditure, equipment orders or site activities satisfy the applicable rules.
Keep the two timing questions separate
| Question | Date or period | Evidence to request |
|---|---|---|
| When did construction begin? | Before 1 January 2028 | Basis for the physical-work or cost route and supporting project documents |
| When does the production-credit period begin? | When the facility is originally placed in service | Placed-in-service date and the facility to which it relates |
| Which production enters the calculation? | Qualified production in the applicable period | Production quantities and required verification |
Sources
- [1] Internal Revenue Service: Instructions for Form 7210 (2025)
Last confirmed: 16 Nov 2026
Eligible production and the credit amount need their own checks
The IRS describes the credit as applying to kilograms of qualified clean hydrogen produced by a taxpayer at a qualified clean hydrogen production facility. The amount depends on production emissions intensity and compliance with prevailing wage and apprenticeship requirements during construction, alteration and repair.
The Form 7210 instructions require production in the United States or a US territory for sale or use in the ordinary course of the taxpayer's trade or business. Production and sale or use must be verified by an unrelated party.
The instructions also say the applicable amount is adjusted annually for inflation. A rate shown for one production year should retain that year in a model. The project must establish the applicable emissions category, labour conditions and year rather than apply a single advertised maximum to all output.
Sources
- [2] Internal Revenue Service: Clean hydrogen production credit
Last confirmed: 16 Nov 2026
- [1] Internal Revenue Service: Instructions for Form 7210 (2025)
Last confirmed: 16 Nov 2026
Carry the conditions into a project comparison
A useful comparison identifies the facility, the taxpayer, the construction basis, the placed-in-service date and the qualified production assumption. It then states the emissions basis, the credit year and the verification documents. These inputs make the proposed support assumption traceable without deciding a particular facility's tax treatment.
The IRS requires a verification report. If a taxpayer petitions for or uses a provisional emissions rate, it also requires the Department of Energy documentation providing an emissions value. Filing and payment arrangements have their own requirements; a construction deadline alone does not establish when cash reaches the project.
This is a timing and evidence screen using the IRS instructions for tax year 2025 and its credit overview. It does not replace the detailed electricity, emissions, labour or tax-filing requirements. Use the instructions for the relevant tax year and check subsequent official developments before relying on a project-specific conclusion.
Sources
- [2] Internal Revenue Service: Clean hydrogen production credit