Inner Mongolia Sustainable Biotechnology Co., Ltd. integrated project to produce green hydrogen, natural gas and multiple coproducts from agricultural and forestry residues
Cancelled
- Capacity
- —
- Target operation
- —
- Technology
- —
- Country
- —
- Development stage
- Cancelled
Project details
- Purpose
- Integrated project to produce green hydrogen, natural gas and multiple coproducts from agricultural and forestry residues
Sources (3)
- The site does not conform to the plan! Inner Mongolia's 700,000-tonne green hydrogen and natural gas project is declared terminated!_Century New Energy Network
Century New Energy Network · As of 2026-09-24
Original value: Integrated project to produce green hydrogen, natural gas and multiple coproducts from agricultural and forestry residues
Original value: The project was not implemented; because the construction site does not meet planning requirements, the project will no longer be implemented (Interruption event: Inner Mongolia Sustainable Biotechnology Co., Ltd. integrated project to produce green hydrogen, natural gas and multiple coproducts from agricultural and forestry residues / The project was not implemented; because the construction site does not meet planning requirements, the project will no longer be implemented)
Original value: Biomass conversion (Pathway: Biomass conversion)
Original value: Reported filing revoked; not implemented and no longer to be implemented due incompatible site planning
Original value: Cancelled
- The site does not conform to the plan! Inner Mongolia's 700,000-tonne green hydrogen and natural gas project is declared terminated!_Century New Energy Network
Century New Energy Network
Original value: Green hydrogen-natural-gas blend and polygeneration: 700,000 tonnes per year (Planned mixed gas and coproducts)
Original value: The project was not implemented; because the construction site does not meet planning requirements, the project will no longer be implemented
- Century New Energy Network
Century New Energy Network
Original value: Reported filing revoked; not implemented and no longer to be implemented due incompatible site planning