H2PrismHydrogen intelligenceSubscribe

Integrated demonstration project for new-energy hydrogen production coproducing carbon-free fuel, with supporting wind and solar power generation

Alkaline

FID / Construction

Capacity
—
Target operation
—
Technology
Alkaline
Country
—
Development stage
FID / Construction

Project details

Interruption
The project failed to start construction on schedule
Product
Hydrogen
Sources (4)
  • Three years of setbacks, and the principal entity changed hands! Huadian takes over the green hydrogen project, and it changes again!

    Century New Energy Network · As of 2026-09-18

    Original value: Alkaline electrolyser (Technology: Alkaline electrolyser)

    Original value: FID / Construction

    Original value: Revised approval reported; current physical operation unverified

    Original value: Hydrogen (Product: Hydrogen)

  • Century New Energy Network

    Century New Energy Network

    Original value: Alkaline electrolyser (Technology: Alkaline electrolyser)

    Original value: Revised approval reported; current physical operation unverified

    Original value: Hydrogen (Product: Hydrogen)

  • Three years of setbacks, and the principal entity changed hands! Huadian takes over the green hydrogen project, and it changes again!

    Century New Energy Network

    Original value: Alkaline electrolyser (Technology: Alkaline electrolyser)

    Original value: The unit's annual hydrogen output is 28,000 tonnes (Hydrogen design annual)

    Original value: Agreed to change the construction content and the investment amount

  • Total investment of 3.589 billion yuan! An Inner Mongolia green hydrogen project is postponed

    Century New Energy Network · As of 2025-10-15

    Original value: The project failed to start construction on schedule (Interruption event: Huadian Tuoyang Darhan Muminggan Banner hydrogen production / The project failed to start construction on schedule)

Related projects