The Three Gorges Group's first integrated comprehensive demonstration project for green hydrogen "production, storage, transport and refueling"
PEM · China
- Capacity
- —
- Target operation
- —
- Technology
- PEM
- Country
- China
- Development stage
- —
Also known as Three Gorges Ulanqab green hydrogen production, storage, transport and refueling integrated comprehensive demonstration project
Project details
- Production pathway
- Electrolysis
- Status
- Commissioning/debugging tests completed; research demonstration
Sources (3)
- Sanxia Jituan's first "production, storage, transport and refueling" green hydrogen project completed commissioning
Energy Sector · As of 2025-11-28
Original value: Electrolysis (Pathway: Electrolysis)
Original value: PEM electrolyser (Technology: PEM electrolyser)
Original value: Commissioning/debugging tests completed; research demonstration
- Energy Sector
Energy Sector
Original value: PEM electrolyser (Technology: PEM electrolyser)
Original value: Commissioning/debugging tests completed; research demonstration
- Sanxia Jituan's first "production, storage, transport and refueling" green hydrogen project completed commissioning
Energy Sector
Original value: PEM electrolyser (Technology: PEM electrolyser)
Sources (2)
- Sanxia Jituan's first "production, storage, transport and refueling" green hydrogen project completed commissioning
Energy Sector · As of 2025-11-28
Original value: Location
- Energy Sector
Energy Sector
Original value: Location
Projects in China
Major projects: operating and FID first, then by recorded capacity.
- CEEC Songyuan Hydrogen Energy Industrial Park (Green H2-NH3 Integration) Phase 2Under construction1,280 MW
- Hydrogen Energy Metallurgical Chemical Demonstration Zone, phase 1FID / Construction750 MW
- Siziwang Banner projectFID / Construction531 MW
- Vision Tongliao Wind-Solar Power to Hydrogen-Ammonia-Methanol Integration ProjectFID / Construction478 MW
- Grove Hydrogen Energy Technology Group hydrogen projectFID / Construction472 MW