Dengkou County grid-connected green-power direct-connection project for hydrogen-based green fuel (hydrogen production portion)
Alkaline · China
- Capacity
- —
- Target operation
- —
- Technology
- Alkaline electrolyser
- Country
- China
- Development stage
- —
Project details
- Product
- Hydrogen
- Process description
- Forms a clear physical boundary with the power grid
- Electricity source
- Renewable
- Function
- Production
Sources (3)
- A direct green-electricity connection project with annual green hydrogen output of 441.99 million Nm3 was approved
Hydrogen Opens the Future · As of 2026-02-24
Original value: Hydrogen (Product: Hydrogen)
Original value: Forms a clear physical boundary with the power grid (Process section: Configuration detail)
Original value: November 2026
Original value: Renewable (Electricity source: Renewable)
Original value: 22 hydrogen production units, each equipped with 4 sets of 1000Nm³/h electrolyzer equipment (22 hydrogen production units, each equipped with 4 sets of 1000Nm³/h electrolyzer equipment)
Original value: Filing reported February2026; construction period remains planned
Original value: Production (Function: Production)
Original value: Alkaline electrolyser (Technology: Alkaline electrolyser)
- A direct green-electricity connection project with annual green hydrogen output of 441.99 million Nm3 was approved
Hydrogen Opens the Future
Original value: Dengkou County, Bayannur, Inner Mongolia (Site: Dengkou County, Bayannur, Inner Mongolia)
Original value: Annual electrolytic hydrogen production of about 39,288 tonnes (Design annual hydrogen mass)
Original value: The total hydrogen production capacity of the alkaline electrolyzers is about 88,000 Nm3/h (88000Nm³/h)
Original value: The project (hydrogen production portion) obtained filing
- Hydrogen Opens the Future
Hydrogen Opens the Future
Original value: Renewable (Electricity source: Renewable)
Original value: 22 hydrogen production units, each equipped with 4 sets of 1000Nm³/h electrolyzer equipment (22 hydrogen production units, each equipped with 4 sets of 1000Nm³/h electrolyzer equipment)
Original value: Filing reported February2026; construction period remains planned
Sources (2)
- A direct green-electricity connection project with annual green hydrogen output of 441.99 million Nm3 was approved
Hydrogen Opens the Future · As of 2026-02-24
Original value: Location
- Hydrogen Opens the Future
Hydrogen Opens the Future
Original value: Location
Projects in China
Major projects: operating and FID first, then by recorded capacity.
- CEEC Songyuan Hydrogen Energy Industrial Park (Green H2-NH3 Integration) Phase 2Under construction1,280 MW
- Hydrogen Energy Metallurgical Chemical Demonstration Zone, phase 1FID / Construction750 MW
- Siziwang Banner projectFID / Construction531 MW
- Vision Tongliao Wind-Solar Power to Hydrogen-Ammonia-Methanol Integration ProjectFID / Construction478 MW
- Grove Hydrogen Energy Technology Group hydrogen projectFID / Construction472 MW