StatusConceptEuropean Clean Hydrogen Partnership · as of 2025
Country · regionSwitzerlandLimeco · as of 2022 · Zurich / ZürichLimeco · as of 2022
TechnologyWater electrolysisEuropean Clean Hydrogen Partnership · as of 2025electrolysis, biological methanation, ex-situ CSTR biomethane reactor, CO2 membraneIEA Bioenergy Task 37
ProductSynthetic renewable gasrenewable biomethane / renewable gas (synthetic methane)Kanadevia Inova · as of 2022
Capacity2.5 MW electrolysis capacity (reported 29 April 2022)

Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis.

Details

Technology & product

Componentswaste incineration plant, wastewater treatment plant, electrolyser, biological methanation plant, gas cleaning unit and CO2 membraneIEA Bioenergy Task 37
Feedstocksewage gas / biogas from the wastewater treatment plant and water for electrolysisLimeco · as of 2022
Final Useinjection into the local gas grid as a CO2-neutral substitute for natural gasKanadevia Inova · as of 2022Injection into the existing gas grid to replace fossil energy carriers
Power Sourceelectricity from the waste incineration plant (WtE/KVA)Limeco · as of 2022Renewable electricity from the waste incineration plant (KVA), as described in 2022
Project Typeindustrial Power-to-Gas (PtG) facility based on biological methanationIEA Bioenergy Task 37

Capacity & economics

Production Volumeup to 18 GWh annually; 1.8 million m³ biomethane per year at full operationSwiss Federal Office of Energy (BFE/SFOE)Planned annual production: approximately 18,000 MWh renewable gas (29 April 2022)
Total CapexCHF 14 millionIEA Bioenergy Task 37

Status & timeline

Lifecycle StageInaugurated on 29 April 2022 (historical milestone)
Eventplant became operational in March 2022; inauguration held 29 April 2022Limeco · as of 2022

Location & names

Site NameLimeco site / Limeco utilityLimeco · as of 2022

Additional project information

Capacity (MW)2.5 MWEuropean Clean Hydrogen Partnership · as of 2025

Timeline

No recorded project events.

Sources & record history

Sources

Field sources

Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.

FieldShown valueOriginal valueSourceDate basisMeaning
NamePtG Switzerland Dietikon
View exact valuePtG Switzerland Dietikon
European Hydrogen Observatory projects Dec2025——
Site NameLimeco site / Limeco utility
View exact valueLimeco site / Limeco utility
Einweihung der ersten industriellen Power-to-Gas-Anlage der Schweiz; Limeco Power to Gas, Dietikon, CHSource dated 2022-04-29Older value (2022)
Administrative AreaZurich / Zürich
View exact valueZurich / Zürich
Einweihung der ersten industriellen Power-to-Gas-Anlage der Schweiz——
CountrySwitzerland
View exact valueSwitzerland
Einweihung der ersten industriellen Power-to-Gas-Anlage der Schweiz——
Componentswaste incineration plant, wastewater treatment plant, electrolyser, biological methanation plant, gas cleaning unit and CO2 membrane
View exact value["waste incineration plant","wastewater treatment plant","electrolyser","biological methanation plant","gas cleaning unit and CO2 membrane"]
Biological Power-2-Gas - LIMECO——
Feedstocksewage gas / biogas from the wastewater treatment plant and water for electrolysis
View exact valuesewage gas / biogas from the wastewater treatment plant and water for electrolysis
Einweihung der ersten industriellen Power-to-Gas-Anlage der Schweiz; Power-to-Gas technical/report publication, document 12157Source dated 2022-04-29Older value (2022)
Final Useinjection into the local gas grid as a CO2-neutral substitute for natural gas
View exact valueinjection into the local gas grid as a CO2-neutral substitute for natural gas
Limeco Power to Gas, Dietikon, CH; Einweihung der ersten industriellen Power-to-Gas-Anlage der SchweizPublication date unknown · accessed 2026-08-28Older value (2022)
Final UseInjection into the existing gas grid to replace fossil energy carriers
View exact valueInjection into the existing gas grid to replace fossil energy carriers
Einweihung der Limeco Power-to-Gas-Anlage——
Power Sourceelectricity from the waste incineration plant (WtE/KVA)
View exact valueelectricity from the waste incineration plant (WtE/KVA)
Einweihung der ersten industriellen Power-to-Gas-Anlage der Schweiz; Biological Power-2-Gas - LIMECOSource dated 2022-04-29Older value (2022)
Power SourceRenewable electricity from the waste incineration plant (KVA), as described in 2022
View exact valueRenewable electricity from the waste incineration plant (KVA), as described in 2022
Einweihung der Limeco Power-to-Gas-Anlage——
ProductSynthetic renewable gas
View exact valueSynthetic renewable gas
Einweihung der Limeco Power-to-Gas-Anlage——
Productrenewable biomethane / renewable gas (synthetic methane)
View exact valuerenewable biomethane / renewable gas (synthetic methane)
Limeco Power to Gas, Dietikon, CH; Einweihung der ersten industriellen Power-to-Gas-Anlage der SchweizPublication date unknown · accessed 2026-08-28Older value (2022)
Project Typeindustrial Power-to-Gas (PtG) facility based on biological methanation
View exact valueindustrial Power-to-Gas (PtG) facility based on biological methanation
Biological Power-2-Gas - LIMECO; Limeco Power to Gas, Dietikon, CHPublication date unknown · accessed 2026-08-28Older value
TechnologyWater electrolysis
View exact valueWater electrolysis
European Hydrogen Observatory projects Dec2025——
Technologyelectrolysis, biological methanation, ex-situ CSTR biomethane reactor, CO2 membrane
View exact value["electrolysis","biological methanation","ex-situ CSTR biomethane reactor","CO2 membrane"]
Biological Power-2-Gas - LIMECO; Power-to-Gas technical/report publication, document 12157; Biological Power-2-Gas - LIMECOPublication date unknown · accessed 2026-08-28Older value
Capacity2.5 MW electrolysis capacity (reported 29 April 2022)
View exact value2.5 MW electrolysis capacity (reported 29 April 2022)
Einweihung der Limeco Power-to-Gas-Anlage——
Production Volumeup to 18 GWh annually; 1.8 million m³ biomethane per year at full operation
View exact valueup to 18 GWh annually; 1.8 million m³ biomethane per year at full operation
Power-to-Gas technical/report publication, document 12157; Biological Power-2-Gas - LIMECOPublication date unknown · accessed 2026-08-28Older value
Production VolumePlanned annual production: approximately 18,000 MWh renewable gas (29 April 2022)
View exact valuePlanned annual production: approximately 18,000 MWh renewable gas (29 April 2022)
Einweihung der Limeco Power-to-Gas-Anlage——
Total CapexCHF 14 million
View exact valueCHF 14 million
Biological Power-2-Gas - LIMECO——
Eventplant became operational in March 2022; inauguration held 29 April 2022
View exact valueplant became operational in March 2022; inauguration held 29 April 2022
Einweihung der ersten industriellen Power-to-Gas-Anlage der Schweiz; Limeco Power to Gas, Dietikon, CHSource dated 2022-04-29Older value (2022)
Lifecycle StageInaugurated on 29 April 2022 (historical milestone)
View exact valueInaugurated on 29 April 2022 (historical milestone)
Einweihung der Limeco Power-to-Gas-Anlage——
Progress StatusConcept
View exact valueannounced_or_planned
European Hydrogen Observatory projects Dec2025——
Capacity (MW)2.5 MW
View exact value2.5 MW
European Hydrogen Observatory projects Dec2025——

Record history

6 current sourced values · 15 older values · Record updated

H2Prism separates published values from estimates. Check the linked source before you use a value. · Back to Hydrogen projects

Records are compiled with AI assistance. Original source links are shown when available.