Limestone Green Hydrogen Production Project

PEM

On hold

Capacity
—
Target operation
2026
Technology
PEM
Country
—
Development stage
On hold

Target operation

2026Target operation
  1. 2024
  2. 2025
  3. 2026
  4. 2027
  5. 2028

Target year as recorded for this project. The axis does not imply stage history.

Project details

Electricity source
Wind
Site
2264 FM209, Graham; unincorporated Young County, Texas
Sources (4)
  • Final Environmental Assessment Limestone Green Hydrogen Production Project, DOE/EA-2281

    U.S. Department of Energy Loan Programs Office

    Original value: Construction is currently paused

    Original value: 2026

    Original value: 45 tpd of liquefied hydrogen (Liquid hydrogen design)

    Original value: PEM electrolyser (Technology: PEM electrolyser)

  • Final Environmental Assessment Limestone Green Hydrogen Production Project, DOE/EA-2281

    U.S. Department of Energy Loan Programs Office · As of 2025-01

    Original value: 2026

    Original value: PEM electrolyser (Technology: PEM electrolyser)

    Original value: Wind (Electricity source: Wind)

    Original value: Construction paused as reported in January2025 EA; initial works existed but manufacturing installation remained planned, no current2026 state inferred

    Original value: On hold

    Original value: 2264 FM209, Graham; unincorporated Young County, Texas (Site: 2264 FM209, Graham; unincorporated Young County, Texas)

  • U.S. Department of Energy Loan Programs Office

    U.S. Department of Energy Loan Programs Office

    Original value: Construction paused as reported in January2025 EA; initial works existed but manufacturing installation remained planned, no current2026 state inferred

  • Plug Power Form10-Q quarter endedJune30,2026

    GL-005:LCF01-S01

    Original value: land and remaining interconnection asset sale not yet closed