GreenH Bodo, phase 1
Overview
StatusFID / ConstructionGreenH
Country · regionNorwayGreenH · NO-18 NordlandGreenH
TechnologyOther ElectrolysisInternational Energy Agency · as of 2026
ProductH2International Energy Agency · as of 2026
Capacity20 MWInternational Energy Agency · as of 2026
Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis. “Other Electrolysis” and “Unknown PtX” are recorded classifications, not a specific electrolyzer design or power-to-X route.
Details
Technology & product
ComponentsOther electrolysisGreenH
Configuration DetailUnknown PtXInternational Energy Agency · as of 2026
Final UseTransportGreenH
Project GroupGreenH Bodø (phase 1)GreenH
Project Typehydrogen production facilityGreenH
Capacity & economics
Production VolumeAnnual hydrogen production capacity of up to 3,100 tonnes (January 2025 plan)
Status & timeline
Date online (tracker field)2026 (meaning under review)International Energy Agency · as of 2026
Location & names
Site NameLangstranda, BodøGreenH
AliasBodø facility; Hydrogen plant at LangstrandaGreenH
Local NameGreen H BodøGreenH
Official NameGreenH BodøGreenH
Additional project information
Administrative AreaLangstranda- BodoInternational Energy Agency · as of 2026
CountryNorwayInternational Energy Agency · as of 2026
Progress StatusFID / ConstructionInternational Energy Agency · as of 2026
Capacity (Announced Size)20 MWInternational Energy Agency · as of 2026
Capacity (Nm³ H₂/h)4,444 Nm³ H₂/hInternational Energy Agency · as of 2026
Capacity (kt H2/y)3.47 kt H2/yInternational Energy Agency · as of 2026
Timeline
- Construction start : 2025-01GreenH
- Final investment decision (FID) : 2025-01-27GreenH
- EPC contract awarded : 2026-01-09NLI
Sources & record history
Sources
- IEA Hydrogen Projects dataset Shared by 12 fields: Snapshot 2026-06-18 · Confidence: reported · Older value (2026)
- GreenH GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/)
- H2Prism earlier record (SRC-C-P200)
- GreenH GreenH and Luxcara make investment decision for hydrogen project in Bodø backed by financing package of NOK 1 billion
- NLI NLI (https://www.nli.no/09-01-2026-new-contract-awarded-by-greenh-bodo-as/)
Field sources
Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.
| Field | Shown value | Original value | Source | Date basis | Meaning |
|---|---|---|---|---|---|
| Name | GreenH Bodo, phase 1 | View exact valueGreenH Bodo, phase 1 | IEA Hydrogen Projects dataset | — | — |
| Site Name | Langstranda, Bodø | View exact value{"text":"Langstranda, Bodø"} | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Administrative Area | NO-18 Nordland | View exact valueNO-18 Nordland | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Alias | Bodø facility; Hydrogen plant at Langstranda | View exact value[{"kind":"source_label","name":"Bodø facility"},{"kind":"source_label","name":"Hydrogen plant at Langstranda"}] | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Country | Norway | View exact valueNOR | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Local Name | Green H Bodø | View exact valueGreen H Bodø | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Official Name | GreenH Bodø | View exact value[{"lang":"en","name":"GreenH Bodø","evidence":["E-01","E-05"]}] | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Components | Other electrolysis | View exact value{"kind":"electrolysis","tech":"OTHER_ELECTROLYSIS","tech_raw":"electrolyser","component_id":"CMP-1"} | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Configuration Detail | Unknown PtX | View exact valueUnknown PtX | IEA Hydrogen Projects dataset | — | — |
| Final Use | Transport | View exact value운송 | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Product | H2 | View exact valueH2 | IEA Hydrogen Projects dataset | — | — |
| Project Group | GreenH Bodø (phase 1) | View exact value{"exists":true,"evidence":["E-03"],"group_name":"GreenH Bodø","phase_name":"phase 1","phase_order":1} | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Project Type | hydrogen production facility | View exact valuehydrogen_production_facility | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Technology | Other Electrolysis | View exact valueOther Electrolysis | IEA Hydrogen Projects dataset | — | — |
| Capacity | 20 MW | View exact value20 MW | IEA Hydrogen Projects dataset | — | — |
| Production Volume | Annual hydrogen production capacity of up to 3,100 tonnes (January 2025 plan) | View exact valueAnnual hydrogen production capacity of up to 3,100 tonnes (January 2025 plan) | GreenH and Luxcara make investment decision for hydrogen project in Bodø backed by financing package of NOK 1 billion | Current | |
| Event | Final investment decision (FID) : 2025-01-27 | View exact value{"date":"2025-01-27","tags":{"as_of":"2025-01","source":"GreenH","evidence":["E-01"],"judged_by":"transcription","confidence":"high","accessed_at":"2026-08-18T00:00:00Z"},"ev_type":"EV-05","event_id":"V-01","raw_date_text":"The board of GreenH Bodø has made a final investment decision","date_precision":"day"} | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Event | Construction start : 2025-01 | View exact value{"date":"2025-01","tags":{"as_of":"2025-01","source":"GreenH","evidence":["E-02"],"judged_by":"transcription","confidence":"high","accessed_at":"2026-08-18T00:00:00Z"},"ev_type":"EV-10","event_id":"V-02","raw_date_text":"We are now moving full speed ahead with the actual construction of the hydrogen facility on the site in Bodø.","date_precision":"month"} | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Event | EPC contract awarded : 2026-01-09 | View exact value{"date":"2026-01-09","tags":{"as_of":"2026-01","source":"NLI","evidence":["E-06"],"judged_by":"transcription","confidence":"high","accessed_at":"2026-08-18T00:00:00Z"},"ev_type":"EV-09","event_id":"V-03","raw_date_text":"NLI Engineering has entred into a contract with GreenH Bodø AS for delivery of fabrication and installation of a new hydrogen plant at Langstranda in Bodø.","date_precision":"day"} | NLI (https://www.nli.no/09-01-2026-new-contract-awarded-by-greenh-bodo-as/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Event | Date online : 2026 | View exact value{"date":"2026","date_precision":"year","event":"Date online","basis":"iea_hydrogen_projects_raw.csv"} | IEA Hydrogen Projects dataset | — | — |
| Progress Status | FID / Construction | View exact valueFID/Construction | GreenH (https://greenh.no/en/greenh-and-luxcara-make-investment-decision/); NLI (https://www.nli.no/09-01-2026-new-contract-awarded-by-greenh-bodo-as/); H2Prism earlier record (SRC-C-P200); H2Prism earlier record (SRC-C-P200) | Older value | |
| Administrative Area | Langstranda- Bodo | View exact valueLangstranda- Bodo | IEA Hydrogen Projects dataset | — | — |
| Country | Norway | View exact valueNorway | IEA Hydrogen Projects dataset | — | — |
| Progress Status | FID / Construction | View exact valueFID/Construction | IEA Hydrogen Projects dataset | — | — |
| Capacity (Announced Size) | 20 MW | View exact value20MW | IEA Hydrogen Projects dataset | — | — |
| Capacity (Nm³ H₂/h) | 4,444 Nm³ H₂/h | View exact value4444.444444444444 Nm³ H₂/h | IEA Hydrogen Projects dataset | — | — |
| Capacity (kt H2/y) | 3.47 kt H2/y | View exact value3.4650666666666665 kt H2/y | IEA Hydrogen Projects dataset | — | — |
Record history
1 current sourced value · 19 older values · Record updated