Green fertilizer project Porsgrunn-Heroya, phase 3 is a hydrogen project in Porsgrunn, Norway using water electrolysis using renewable energy; recorded capacity: 24 MW.

Overview

Statusoperating and producing renewable hydrogen/ammonia by 2024
Country · regionNorway · Porsgrunn
Technologywater electrolysis using renewable energy
ProductAmmoniaammonia; mineral fertilizerYara International
Capacity24 MW

Capacity values retain their recorded units and scope. MW, kt H₂/y and Nm³ H₂/h are different measures; this page does not convert or add them without a shared operating basis. “Other Electrolysis” and “Unknown PtX” are recorded classifications, not a specific electrolyzer design or power-to-X route.

Details

Technology & product

Carbon Reduction41,000 tonnes CO2 per year
Componentselectrolysis plant; ammonia plant; fertilizer production chain
Configuration DetailUnknown PtX
Final Usefertilizer; shipping fuel (intended/possible uses; fertilizer delivery evidenced)
Power Sourcerenewable energy
Project Typegreen ammonia / renewable hydrogen demonstration plant

Capacity & economics

Awarded PriceNOK 283.25 million Enova support
FinancingEnova support; funds subject to ESA approval
Production Volume20,500 tonnes ammonia per year; 60,000–80,000 tonnes mineral fertilizer equivalent per year

Status & timeline

Actual Outputfirst tonnes of low-carbon-footprint fertilizer delivered to Lantmännen
Lifecycle Stageopened / operating
EventMarch 2022 groundbreaking for pilot project; June 2024 official opening

Location & names

Site NameHerøya Industrial Park
External Identifier1279

Additional project information

CountryNorwayInternational Energy Agency · as of 2026
Progress StatusCancelledInternational Energy Agency · as of 2026
Configuration DetailUnknown PtXInternational Energy Agency · as of 2026
ProductAmmoniaInternational Energy Agency · as of 2026
TechnologyOther ElectrolysisInternational Energy Agency · as of 2026

Timeline

No recorded project events.

Sources & record history

Sources

Field sources

Shared date, confidence and value status appear once with their source above; a dash in the table refers to that source context.

FieldShown valueOriginal valueSourceDate basisMeaning
NameGreen fertilizer project Porsgrunn-Heroya, phase 3
View exact valueGreen fertilizer project Porsgrunn-Heroya, phase 3
Yara and Linde Engineering agree to build a 24 MW green hydrogen demonstration plant in Norway. Both companies aim to achieve a significant carbon dioxide reduction in the production of fertilizers in Norway—
Site NameHerøya Industrial Park
View exact valueHerøya Industrial Park
Yara opens renewable hydrogen plant: “A major milestone”—
Administrative AreaPorsgrunn
View exact valuePorsgrunn
Yara begins electrifying the factory at HerøyaCurrent
CountryNorway
View exact valueNOR
Yara and Linde Engineering agree to build a 24 MW green hydrogen demonstration plant in Norway. Both companies aim to achieve a significant carbon dioxide reduction in the production of fertilizers in Norway—
External Identifier1279
View exact value1279
Yara and Linde Engineering agree to build a 24 MW green hydrogen demonstration plant in Norway. Both companies aim to achieve a significant carbon dioxide reduction in the production of fertilizers in Norway—
Carbon Reduction41,000 tonnes CO2 per year
View exact value41,000 tonnes CO2 per year
Yara opens renewable hydrogen plant: “A major milestone”—
Componentselectrolysis plant; ammonia plant; fertilizer production chain
View exact valueelectrolysis plant; ammonia plant; fertilizer production chain
Yara opens renewable hydrogen plant: “A major milestone”—
Configuration DetailUnknown PtX
View exact valueUnknown PtX
Yara and Linde Engineering agree to build a 24 MW green hydrogen demonstration plant in Norway. Both companies aim to achieve a significant carbon dioxide reduction in the production of fertilizers in Norway—
Final Usefertilizer; shipping fuel (intended/possible uses; fertilizer delivery evidenced)
View exact valuefertilizer; shipping fuel (intended/possible uses; fertilizer delivery evidenced)
Yara begins electrifying the factory at HerøyaCurrent
Power Sourcerenewable energy
View exact valuerenewable energy
Yara opens renewable hydrogen plant: “A major milestone”—
ProductAmmonia
View exact valueAmmonia
Yara and Linde Engineering agree to build a 24 MW green hydrogen demonstration plant in Norway. Both companies aim to achieve a significant carbon dioxide reduction in the production of fertilizers in Norway—
Productammonia; mineral fertilizer
View exact valueammonia; mineral fertilizer
Yara begins electrifying the factory at HerøyaOlder value
Project Typegreen ammonia / renewable hydrogen demonstration plant
View exact valuegreen ammonia / renewable hydrogen demonstration plant
Yara begins electrifying the factory at HerøyaCurrent
Technologywater electrolysis using renewable energy
View exact valuewater electrolysis using renewable energy
Yara opens renewable hydrogen plant: “A major milestone”—
Awarded PriceNOK 283.25 million Enova support
View exact valueNOK 283.25 million Enova support
Yara begins electrifying the factory at HerøyaCurrent
Capacity24 MW
View exact value24 MW
Yara opens renewable hydrogen plant: “A major milestone”—
FinancingEnova support; funds subject to ESA approval
View exact valueEnova support; funds subject to ESA approval
Yara begins electrifying the factory at HerøyaCurrent
Production Volume20,500 tonnes ammonia per year; 60,000–80,000 tonnes mineral fertilizer equivalent per year
View exact value20,500 tonnes ammonia per year; 60,000–80,000 tonnes mineral fertilizer equivalent per year
Yara begins electrifying the factory at HerøyaCurrent
Actual Outputfirst tonnes of low-carbon-footprint fertilizer delivered to Lantmännen
View exact valuefirst tonnes of low-carbon-footprint fertilizer delivered to Lantmännen
Yara opens renewable hydrogen plant: “A major milestone”—
EventMarch 2022 groundbreaking for pilot project; June 2024 official opening
View exact valueMarch 2022 groundbreaking for pilot project; June 2024 official opening
Yara fortsetter arbeidet med å kutte Norges største punktutslippCurrent
Lifecycle Stageopened / operating
View exact valueopened / operating
Yara opens renewable hydrogen plant: “A major milestone”—
Progress Statusoperating and producing renewable hydrogen/ammonia by 2024
View exact valueoperating and producing renewable hydrogen/ammonia by 2024
Yara opens renewable hydrogen plant: “A major milestone”—
CountryNorway
View exact valueNorway
IEA Hydrogen Projects dataset——
Progress StatusCancelled
View exact valueCancelled
IEA Hydrogen Projects dataset——
Configuration DetailUnknown PtX
View exact valueUnknown PtX
IEA Hydrogen Projects dataset——
ProductAmmonia
View exact valueAmmonia
IEA Hydrogen Projects dataset——
TechnologyOther Electrolysis
View exact valueOther Electrolysis
IEA Hydrogen Projects dataset——

Record history

20 current sourced values · 1 older value · Record updated

H2Prism separates published values from estimates. Check the linked source before you use a value. · Back to Hydrogen projects

Records are compiled with AI assistance. Original source links are shown when available.