Progress StatusPS-01Confidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
CountryGermanyConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Capacity100 MWEarlier record
Original source not yet verified
Original source not yet verified
LocationView on map →
Project Identity and Location
Public NameGET H2 NukleusConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Site NameEmsland gas-fired power plant site, LingenConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Administrative AreaDE-NIConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
AliasGET H₂ NukleusConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Show 2 moreHide 2
External IdentifierP200-0037Confidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Official NameGET H2 NukleusConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Project Purpose and Configuration
ComponentsComponent Id: CMP-1; Kind: electrolyser; Tech: PEM; Tech Raw: PEM electrolysisConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Project GroupEvidence: E-01, E-02; Exists: true; Group Name: GET H2 Nukleus; Phase Name: Phase 1: first 100 MW PEM electrolysis unit; Phase Order: 1Confidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Project Typehydrogen_production_facilityConfidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Project Lifecycle and Change
Lifecycle StageLS-04Confidence: Reported
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Source: Capacity reservation with RWE for 150MW of NEPTUNE V units
Earlier records
ProductH2Earlier record
Original source not yet verified
Original source not yet verified
TechnologyPEMEarlier record
Original source not yet verified
Original source not yet verified
Target year2026Earlier record
Original source not yet verified
Original source not yet verified
Secondary research context
Tracker snapshots are supporting research, not verified project facts. They stay separate from the sourced-value count and do not replace confirmed values.
Administrative AreaLingen RWE plantSecondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
CountryGermanySecondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Public NameGET H2 Nukleus, phase 1Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Event2026Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Show 7 moreHide 7
Progress StatusFID/ConstructionSecondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
ProductH2Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
TechnologyPEMSecondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Capacity300 MW total (100MW phase 1)Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Capacity14.993Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Capacity19,230.769Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Capacity100Secondary source
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Confidence: Reported
Snapshot 2026-06-18
Source: Secondary source · International Energy Agency
Sources
| Source | Type | Publisher | As of |
|---|---|---|---|
| Capacity reservation with RWE for 150MW of NEPTUNE V units | Original source | itm-power.com |